This page contains a list of scheduled project events, and key
milestones and deliverables.
Upcoming milestones and deadlines:
July 23-27, 2001: PRIMER flight week on KC-135 out of NASA GRC.
Schedule as of May 4, 2001:
|
REVISED SCHEDULE (After the meeting) |
|
|
Month |
Start Month |
End Month |
Tasks |
Milestone |
|
0 |
1-Mar-01 |
1-Apr-01 |
|
|
|
1 |
1-Apr-01 |
1-May-01 |
trade study/design/ proof of concept |
|
|
2 |
1-May-01 |
1-Jun-01 |
trade study/design/ proof of concept |
trade study complete |
|
|
|
|
|
PDR |
|
3 |
1-Jun-01 |
1-Jul-01 |
Fabricate prototype (PRIMER) |
prototype prints complete |
|
|
|
|
Fabricate prototype door/launcher |
|
|
4 |
1-Jul-01 |
1-Aug-01 |
Final testing of PRIMER |
prototype fabrication complete |
|
5 |
1-Aug-01 |
1-Sep-01 |
prototype door/launcher functional tests |
CDR |
|
|
|
|
|
Design for manufacturability review |
|
6 |
1-Sep-01 |
1-Oct-01 |
flight design 1 |
|
|
7 |
1-Oct-01 |
1-Nov-01 |
flight design 2 |
flight design complete (15-Oct-01) |
|
|
|
|
build 2nd prototype (flight box 1) |
prototype fabrication complete (1-Nov-01) |
|
8 |
1-Nov-01 |
1-Dec-01 |
Test flight box 1 |
testing (2 weeks) |
|
|
|
|
Update/corrections on flight box 1 |
(2 weeks) |
|
9 |
1-Dec-01 |
1-Jan-02 |
contingency |
|
|
10 |
1-Jan-02 |
1-Feb-02 |
machining flight hardware |
|
|
11 |
1-Feb-02 |
1-Mar-02 |
fit checks, assembly |
all units machined, and completely assembled |
|
|
|
|
Frame for structure |
Frame completed |
|
12 |
1-Mar-02 |
1-Apr-02 |
test and calibration |
testing complete |
|
13 |
1-Apr-02 |
1-May-02 |
contingency |
|
|
14 |
1-May-02 |
1-Jun-02 |
contingency |
flight 02-Jun-02 |