This page contains a list of scheduled project events, and key milestones and deliverables.

Upcoming milestones and deadlines:

July 23-27, 2001: PRIMER flight week on KC-135 out of NASA GRC.

 

Schedule as of May 4, 2001:

REVISED SCHEDULE (After the meeting)

Month

Start Month

End Month

Tasks

Milestone

0

1-Mar-01

1-Apr-01

1

1-Apr-01

1-May-01

trade study/design/ proof of concept

2

1-May-01

1-Jun-01

trade study/design/ proof of concept

trade study complete

PDR

3

1-Jun-01

1-Jul-01

Fabricate prototype (PRIMER)

prototype prints complete

Fabricate prototype door/launcher

4

1-Jul-01

1-Aug-01

Final testing of PRIMER

prototype fabrication complete

5

1-Aug-01

1-Sep-01

prototype door/launcher functional tests

CDR

Design for manufacturability review

6

1-Sep-01

1-Oct-01

flight design 1

7

1-Oct-01

1-Nov-01

flight design 2

flight design complete (15-Oct-01)

build 2nd prototype (flight box 1)

prototype fabrication complete (1-Nov-01)

8

1-Nov-01

1-Dec-01

Test flight box 1

testing (2 weeks)

Update/corrections on flight box 1

(2 weeks)

9

1-Dec-01

1-Jan-02

contingency

10

1-Jan-02

1-Feb-02

machining flight hardware

11

1-Feb-02

1-Mar-02

fit checks, assembly

all units machined, and completely assembled

Frame for structure

Frame completed

12

1-Mar-02

1-Apr-02

test and calibration

testing complete

13

1-Apr-02

1-May-02

contingency

14

1-May-02

1-Jun-02

contingency

flight 02-Jun-02

 

PRIMER Schedule as of May 4, 2001:

PRIMER

Month

Start Month

End Month

Task

Milestone

1

1-Apr-01

1-May-01

2

1-May-01

1-Jun-01

Sample design/plan/prints

Design complete

Vaccum system set up

Vaccum system complete and functional

3

1-Jun-01

1-Jul-01

Build/test

Prepare SDP

JUNE 15th (SAFETY DATA PACKAGE)

4

1-Jul-01

1-Aug-01

final testing/corrections

JULY 23rd (flight)

 