|
Meetings
SORCE is tentatively
scheduling a Science Meeting July 9, 10, 11 2001 at the Laboratory for
Atmospheric and Space Physics, University of Colorado, Boulder, Colorado.
We would like feedback from SORCE Science Team Members on the proposed
dates for the meeting. Please contact kathy.lozier@lasp.colorado.edu
Gary Rottman, Tom Woods, and Greg Kopp, attended an EOS IWG meeting
in Ft. Lauderdale, Florida on January 30 to February 1.
The SORCE QED (Quarterly Executive Dialog) was held at LASP January
30, 2001, and resulted in a positive evaluation for SORCE.
SORCE
January 2001 Project Summary
Visitors from TRW Corporation attended the SORCE January Monthly
Review to obtain an overview of the SORCE experiment and the LASP
working environment, in order to evaluate possible future joint
endeavors with LASP.
The EOS SORCE mission is scheduled for a launch date of July 2002. The
SORCE program is on schedule and within budget. No mission descopes
are envisioned at this time.
The SORCE Red Team has been redefined, and the Aerospace Corporation
will now assume the role. The Red Team will attend all major SORCE
reviews and make recommendations to SORCE based on their observations.
SORCE and the Aerospace Corporation met January 23-24 to develop
SORCE FTA (fault tree analysis), FMEA (failure modes and effects
analysis) and PRA (probability risk assessment) documents. The
Aerospace Corporation was favorably impressed with the SORCE program's
electrical engineering, design redundancy, and ability to acquire
science data.
SORCE continues to closely monitor and adjust schedules for instrument
fabrication to respond to changing priorities and availability
of facilities during fabrication and test. There are currently
two major delays to spacecraft development, one is the 3 to 6
week delay in the delivery of the instrument bench, and the other
is a 2 to 4 month delay in the SORCE receiving transponder. SORCE
Team Members attended the Alenia Transceiver Critical Design Review
in early February and so far, the late delivery of the transceiver
has not directly impacted the bus I & T schedule.
The SORCE budget contingency continues to be depleted, largely due to
the high cost of parts and outside electronic board manufacture. To
date, SORCE contingency has been able to accommodate these rising costs.
Schedule slack time in the SORCE program is an ongoing concern.
SOLSTICE slack has dissipated, due to the late delivery of flight
subassemblies. The calibration plan for SOLSTICE is undergoing
reevaluation, and rescheduling may recover time. SIM schedule
slack is also small. An effort is un-
|
derway to acquire
additional calibration support for SIM. All aspects of SIM manufacture
are monitored daily.
The overcrowding of test facilities for all SORCE instruments
is a problem. SORCE has scheduled testing facilities at Ball Aerospace,
reworked testing schedules and purchased additional bench test
equipment in order to alleviate this situation.
The question of IFOG (gyros) for the spacecraft is still an issue.
The IFOG manufacture and reliability has been considered a risk
to mission success. Orbital has constructed a study to determine
ACS control system performance in the absence of IFOGs. It appears
that the SORCE spacecraft could still fly with the ACS system
if the IFOGs failed or were removed from the spacecraft.
Mass models of SIM, SOLSTICE A and B, and TIM have been shipped to Orbital.
TIM
Status
Excellent progress has been made on TIM. All TIM parts are at
LASP except for the kinematic mounts. TIM apertures are flyable,
but measurements do not yet have an absolute accuracy of 25 ppm.
Continued work on stray light scattering and internal reflections
is ongoing.
SIM
Status
SIM is being readied for flight build and will require 8 weeks
for completion. A build plan has been devised and partial assembly
and testing has begun.
SOLSTICE
Status
The SOLSTICE instrument is also in the processes of integration,
calibration and testing. Mechanical/optical integration is complete
and imaging performance meets or exceeds requirements. Flight
detector integration and GCI integration is finished. Flight grating
drive shortterm repeatability and accuracy exceed requirements,
but the grating drive exhibits sensitivity to external disturbances,
and fixes are under consideration.
SORCE
Data System Status
SORCE database traceability and reproducibility model has been
completed. The managed data product software layer is nearly completed,
and is now being used by other programmers as the basis for developing
data product code. The Java Database interface layer has been
enhanced in the last month, and is now utilized for algorithm
development. The direct IDL interface of the Sybase database is
complete and in the maintenance cycle. Telemetry ingest is undergoing
initial testing. The conversion of SOLSTICE algorithms from UARS
is almost finished. Ancillary services development is nearly done.
SORCE has ongoing monthly telecons with ESDIS (Earth Science Data
and Information System). The Memo-randum of Understanding between
SORCE and
|