Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Goal: to complete the transfer of MEC data processing to LASP by 9/30/2023

Bi-weekly tagup (MEC Team at LANL + SDC leads + PS Office): Occurs every 2 weeks on Wednesday effective 2/8/23 from 3:00 PM to 3:15 PM ET.

https://nasaenterprise.webex.com/nasaenterprise/j.php?MTID=m8d16bfe9b92d6d1e59ee9045ff96d039

2/8 tagup summary: Kris will set up the technical meeting with Steve (and Mike, if available) and SDC dev team Adrian/Michael, to occur on 2/15 at 3PM ET.


MEC -> SDC Transition Timeline  (DRAFT by Kris Larsen)

February 1-7, 2023 → rescheduled to 2/15 with an enhanced agenda

     SDC-LANL Technical Meeting (virtual)

     Agenda

  • SDC Virtual Machine Requirements
    1. Memory requirements
    2. Processing Cores
    3. Ubuntu version
    4. Software Dependencies
  • MEC Docker Specifications

March 2023

     Establish a virtual machine at the SDC to prepare for LANL docker

                        Including processing triggers

April/May

     Delivery of LANL Docker to SDC

                        Integration of Docker into SDC pipeline

                        Initial validation of data products

June 2023   

      Create MEC data products at the SDC

July/August 2023

     Dual Generation Period

     Products created at both SDC and LANL

  • LANL products continue as official (served to public and archived at SPDF)
  • SDC products checked against LANL for validity and completenss

September 2023

     Transition Complete