Draft Instructions from HQ SMD
2March2026 Draft Call for Proposals
Proposal Content
- Completion of Previous Science Objectives
- Proposed Extended Mission Science Objectives
- Over-guide Requests (Optional)
- Transition Plan to Competitively Funded Research (Transition Science proposals only):
- Contributions to the HSO and National Priorities:
- Current Mission Status
- Proposed Extended Mission Operations
- Management Plan
- Data and Code Management Plan
- Budget Narrative
- Backup Material
- Acronym List:
- References:
- Team Publications:
- External Publications:
- Additional Documents
- Budget Spreadsheet(s)
- Project Data Management Plan (PDMP)
- Calibration and Measurement Algorithms Document (CMAD)
Draft Schedule:
Draft Call for Proposals Issued | March 2, 2026 |
Pre-Proposal Briefing to Mission Teams | March 5, 2026 |
Final Call for Proposals Issued | March 2026 |
Senior Review Proposals Due | May 2026 |
Mission Presentations to Senior Review Panel | May 2026 |
Draft Senior Review Recommendations to HPD | May 2026 |
Senior Review Panel Report Delivered to HPD | June 2026 |
HPD Response and Letters of Direction to missions | August 2026 (NET) |
Publication of Senior Review Panel Report | August 2026 (NET) |
Development Schedule
SR writing team through April 30: intro/front matter, accomplishments, science objectives & contributions to HSO, operations & campaigns, data archive / status, management plan
FR phase planning through April 6 (and as needed April 6-30): including refocused tetrahedron campaign planning, in- and over-guide extended mission definitions
CFR phase planning through April 6 (and as needed April 6-30): planning Links-like phase, operational cost reduction, transition to competitively funded science, etc +Bob Ergun
through April 30: Budget planning FY27-31
through Mar 1: SWT prepares white papers
Feb 13: review slide outline, assign sections
Feb 13 - Mar 15: storyboarding, draft/sketch figures needed per slide
Feb 16: draft AO released → received 2 March 2026
Feb 23: pre-proposal conference → now 5 March 2026 at 1pm ET
Mar 1: white papers submitted to Fuselier, Genestreti, disseminated to goals/objectives section writers
Mar 1 - 15: define science goals and objectives
- Mar 5: pre-proposal conference
Mar tbd: final AO released
Mar 15: final definition of science goals and objectives
Mar 15 - April 6: graphics
April 6: all remaining material to be submitted to Sr Review team
April 6 - 10: production of complete slide stack
April 10: practice presentation to SWG
April 10 - 17: incorporate SWG comments into slides
April 17: red team presentation
April 17 - 21: red team deliberates
April 21: red team report submitted to Sr. Rev. team
April 21 - 30: incorporate red team comments into slides
NLT May 1: Final slides submitted