Draft Instructions from HQ SMD

2March2026 Draft Call for Proposals

Proposal Content

  1. Completion of Previous Science Objectives
  2. Proposed Extended Mission Science Objectives
    1. Over-guide Requests (Optional)
  3. Transition Plan to Competitively Funded Research (Transition Science proposals only):
  4. Contributions to the HSO and National Priorities:
  5. Current Mission Status
  6. Proposed Extended Mission Operations
  7. Management Plan
  8. Data and Code Management Plan
  9. Budget Narrative
  10. Backup Material
    1. Acronym List:
    2. References:
    3. Team Publications:
    4. External Publications:
  11. Additional Documents
    1. Budget Spreadsheet(s)
    2. Project Data Management Plan (PDMP)
    3. Calibration and Measurement Algorithms Document (CMAD)


Draft Schedule:

Draft Call for Proposals Issued

March 2, 2026

Pre-Proposal Briefing to Mission Teams

March 5, 2026

Final Call for Proposals Issued

March 2026

Senior Review Proposals Due

May 2026

Mission Presentations to Senior Review Panel

May 2026

Draft Senior Review Recommendations to HPD

May 2026

Senior Review Panel Report Delivered to HPD

June 2026

HPD Response and Letters of Direction to missions

August 2026 (NET)

Publication of Senior Review Panel Report

August 2026 (NET)




Development Schedule

SR writing team through April 30: intro/front matter, accomplishments, science objectives & contributions to HSO, operations & campaigns, data archive / status, management plan

FR phase planning through April 6 (and as needed April 6-30): including refocused tetrahedron campaign planning, in- and over-guide extended mission definitions

CFR phase planning through April 6 (and as needed April 6-30): planning Links-like phase, operational cost reduction, transition to competitively funded science, etc +Bob Ergun

through April 30: Budget planning FY27-31

through Mar 1: SWT prepares white papers

 

  • Feb 13: review slide outline, assign sections

  • Feb 13 - Mar 15: storyboarding, draft/sketch figures needed per slide

  • Feb 16: draft AO released → received 2 March 2026

  • Feb 23: pre-proposal conference → now 5 March 2026 at 1pm ET

  • Mar 1: white papers submitted to Fuselier, Genestreti, disseminated to goals/objectives section writers

  • Mar 1 - 15: define science goals and objectives

  • Mar 5: pre-proposal conference
  • Mar tbd: final AO released

  • Mar 15: final definition of science goals and objectives

  • Mar 15 - April 6: graphics

  • April 6: all remaining material to be submitted to Sr Review team

  • April 6 - 10: production of complete slide stack

  • April 10: practice presentation to SWG

  • April 10 - 17: incorporate SWG comments into slides

  • April 17: red team presentation

  • April 17 - 21: red team deliberates

  • April 21: red team report submitted to Sr. Rev. team

  • April 21 - 30: incorporate red team comments into slides

  • NLT May 1: Final slides submitted