Goal: to complete the transfer of MEC data processing to LASP by 9/30/2023

Bi-weekly tagup (MEC Team at LANL + SDC leads + PS Office) 


MEC -> SDC Transition Timeline  (DRAFT by Kris Larsen)

February 1-7, 2023:

     SDC-LANL Technical Meeting (virtual)

     Agenda

  • SDC Virtual Machine Requirements
    1. Memory requirements
    2. Processing Cores
    3. Ubuntu version
    4. Software Dependencies
  • MEC Docker Specifications

March 2023

     Establish a virtual machine at the SDC to prepare for LANL docker

                        Including processing triggers

April/May

     Delivery of LANL Docker to SDC

                        Integration of Docker into SDC pipeline

                        Initial validation of data products

June 2023   

      Create MEC data products at the SDC

July/August 2023

     Dual Generation Period

     Products created at both SDC and LANL

  • LANL products continue as official (served to public and archived at SPDF)
  • SDC products checked against LANL for validity and completenss

September 2023

     Transition Complete