  • The plan had been to start acoustics testing on Thursday (6/27). Because of delays in completing the necessary final spacecraft assembly and solar array test activities, the window of opportunity with the acoustics test facility was missed, so the current plan is to move forward with vibration testing instead. The acoustic test timeframe is now TBD.
  • Solar array deploy testing is expected to begin today and run into tomorrow.
  • Vibration test start is now scheduled for late Friday afternoon (6/28) following a Thursday afternoon pre-test briefing. The plan is to complete all three axis prior to the 4th of July holiday. Operations at OSC will be shut down from 7/4-7/7 for a short holiday break.
Share this post:
See Also
March 6, 2020
Good-bye SORCE, Hello TSIS !

The NASA Solar Radiation and Climate Experiment (SORCE) science mission ended on February 25, 2020 after completing more than 17 […]

view post >>
July 24, 2019
TCTE Mission Ends

As planned, the Total Solar Irradiance Calibration Transfer Experiment (TCTE) science mission ended on June 30, 2019. TCTE was built […]

view post >>
July 15, 2019
SORCE Operations Extended to January 2020

Great news for the SORCE mission! After a Key Decision Point (KDP) Meeting regarding SORCE’s Phase F, NASA Headquarters has […]

view post >>
Scroll to Top