Goal: to complete the transfer of MEC data processing to LASP by 9/30/2023
Bi-weekly tagup (MEC Team at LANL + SDC leads + PS Office): Occurs every 2 weeks on Wednesday effective 2/8/23 from 3:00 PM to 3:15 PM ET.
https://nasaenterprise.webex.com/nasaenterprise/j.php?MTID=m8d16bfe9b92d6d1e59ee9045ff96d039
2/8 tagup (Kris, Steve, Li-Jen) summary: Kris will set up the technical meeting with Steve (and Mike, if available) and SDC dev team Adrian/Michael, to occur on 2/15 at 3PM ET.
MEC -> SDC Transition Timeline (DRAFT by Kris Larsen)
February 1-7, 2023 → rescheduled to 2/15 with an enhanced agenda
SDC-LANL Technical Meeting (virtual)
Agenda
- SDC Virtual Machine Requirements
- Memory requirements
- Processing Cores
- Ubuntu version
- Software Dependencies
- MEC Docker Specifications
March 2023
Establish a virtual machine at the SDC to prepare for LANL docker
Including processing triggers
April/May
Delivery of LANL Docker to SDC
Integration of Docker into SDC pipeline
Initial validation of data products
June 2023
Create MEC data products at the SDC
July/August 2023
Dual Generation Period
Products created at both SDC and LANL
- LANL products continue as official (served to public and archived at SPDF)
- SDC products checked against LANL for validity and completenss
September 2023
Transition Complete