Goal: to complete the transfer of MEC data processing to LASP by 9/30/2023
Bi-weekly tagup (MEC Team at LANL + SDC leads + PS Office): Occurs every 2 weeks on Wednesday effective 2/8/23 from 3:00 PM to 3:15 PM ET.
https://nasaenterprise.webex.com/nasaenterprise/j.php?MTID=m8d16bfe9b92d6d1e59ee9045ff96d039
2/8 tagup (Kris, Steve, Li-Jen) summary: Kris will set up the technical meeting with Steve (and Mike, if available) and SDC dev team Adrian/Michael, to occur on 2/15 at 3PM ET.
MEC -> SDC Transition Timeline (DRAFT by Kris Larsen)
February 1-7, 2023 → rescheduled to 2/15 with an enhanced agenda
SDC-LANL Technical Meeting (virtual)
Agenda
- SDC Virtual Machine Requirements
- Memory requirements
- Processing Cores
- Ubuntu version
- Software Dependencies
- MEC Docker Specifications
March 2023
Establish a virtual machine at the SDC to prepare for LANL docker
LASP will file ticket with LASP IT on February 22 (intend to have VM established by Feb 28th.)
LASP will establish accounts and verify access with Steve
Initial Install tests by Steve by approximately March 10th (or 24th)
April/May
Delivery of LANL Code to SDC
Integration of LANL Code into SDC pipeline
Connect LANL code to SDC file storage
Initial validation of data products
Investigate Processing triggers
Based on current LANL cron-based trigger system
June 2023
Create MEC data products at the SDC
July/August 2023
Dual Generation Period
Products created at both SDC and LANL
- LANL products continue as official (served to public and archived at SPDF)
- SDC products checked against LANL for validity and completenss
September 2023
Transition Complete